kawasan industri gresik jiipe

JIIPE Industrial Estate

Industrial Area | 1761 ha land area

Competitive and Sustainable Independent Utilities

Spanning 1,761 hectares within JIIPE’s master-planned ecosystem, our Technology and Manufacturing Special Economic Zone (SEZ) delivers future-ready infrastructure engineered to support large-scale, uninterrupted industrial operations. Recognizing that energy security and logistics efficiency are vital to global competitiveness, JIIPE provides comprehensive, independent utilities—ranging from high-capacity power plants and dedicated gas pipelines to centralized water and wastewater treatment facilities, alongside high-speed fiber-optic telecommunications. Master-planned to strict Green Industrial Estate standards in a guaranteed flood-free zone, the industrial area connects directly to our Multipurpose Deep Sea Port and features a modern cluster-based zoning system that fosters seamless, secure, and sustainable supply chain synergy among tenants.

Industrial Area Clustering:

kawasan industri gresik jiipe

JIIPE Industrial Estate`s Featured Features in Gresik

Complete Facilities and Infrastructure Complete Facilities and Infrastructure
  • International standard road system, with ROW 80 m, 50 m, 30m
  • Lots for heavy, medium and light industries
  • Office building and commercial area
  • Direct piping connection and conveyor
  • Bonded Zone, Bonded Logistic Center & Bonded Warehouse
  • Single window processing system for ease of doing business
  • Direct construction license (KLIK)
Logistics Efficiency Planning Logistics Efficiency Planning
  • Well-planned clustering to avoid contamination and enhance operation sustainability.
  • Pipe racks and liquid jetty to support liquid based industries
  • Logistics cost for incoming raw materials and distribution of finished goods will be competitive with utilization of JIIPE 3 modes of sea and land connectivity (deep- sea port, railway, toll road)
Connectivity Connectivity
  • Deep-sea port –16 LWS.
  • Direct toll road connection from Surabaya as the second largest city in Indonesia.
  • Double track railway access, connected to access points in Java Island
kawasan industri gresik jiipe

Energy Sources and Advanced Processing Facilities in JIIPE Industrial Estates

Power Plant

A reliable, multi-source power supply combining gas-fired generation, renewable energy and the national grid, planned to reach a total capacity of 3,048 MVA by 2040.

PHASE 1 (up to 2026–2030)

  • Gas Engine Power Plant (PLTMG): 23 MVA
  • Supply from PT PLN: 710 MVA

PHASE 2 (2031–2035)

  • Combined Cycle Power Plant (PLTGU): 500 MVA
  • Floating Solar Power Plant: 148 MVA
  • Tenant Rooftop Solar: 70 MVA
  • Additional supply from PT PLN: 90 MVA

PHASE 3 (2036–2040)

  • Additional supply from PT PLN: 1,507 MVA

Water Treatment Plant

We supply industrial water from multiple sources to secure operational reliability, reduce production costs and support environmental compliance, with a total planned capacity of 3,568 lps (308,287 m³/day).

PHASE 1 (up to 2026–2030)

  • 28 lps (2,400 m³/day) Sea Water Reverse Osmosis (SWRO) BKMS
  • 17 lps (1,500 m³/day) WTP BKMS
  • 600 lps from PT PDAM
  • 833 lps Desalination BKMS

PHASE 2 (2031–2035)

  • 250 lps additional supply from PT PDAM
  • 920 lps Desalination BKMS

PHASE 3 (2036–2040)

  • 920 lps Desalination BKMS

Waste Water Treatment Plant

Centralized waste water treatment facilities developed in stages, reaching a total capacity of 117,500 m³/day.

  • PHASE 1: 17,500 m³/day (WWTP-1: 2,500 m³/day, WWTP-2: 15,000 m³/day)
  • PHASE 2: 50,000 m³/day (WWTP-3 & WWTP-4, 25,000 m³/day each)
  • PHASE 3: 50,000 m³/day (WWTP-5 & WWTP-6, 25,000 m³/day each)

Natural Gas

Natural gas is delivered through PT BKMS’s own pipeline network, from the metering point to each tenant’s delivery point.

  • 16" main pipeline: 5,403 m
  • 12" secondary pipeline: 5,102 m
  • Maximum supply capacity: 93.03 MMBTU
kawasan industri gresik jiipe

Efficiency of Business Opening in JIIPE Gresik Industrial Area

Single Window Processing System

Single Window Processing System

3 Hour Service from Indonesia Investment Coordinating Board for initial approval and licensing process. JIIPE facilitates industrial investors to the related parties for permits and licensing requirements.

Direct Construction License

Direct Construction License

Utilizing Direct Construction License from Indonesia Investment Coordination Board, industrial tenants could build their factories and right after their construction design is approved by JIIPE Estate Management, in parallel processing their building permit.

Industrial Zoning

Industrial Zoning

  • Combined zone for manufacturing industry
  • Combined zone for warehousing
  • Combined zone for logistics center

Appointment for Industrial Land Acquisition /
Request for Proposal

This form is only for businesses genuinely interested in acquiring industrial land within JIIPE SEZ.
Please provide accurate details to help us assess your needs and offer the best solutions.

All fields marked with an asterisk (*) are mandatory

Basic Information

The reason for considering JIIPE ? *
(Ha)

Energy & Utility Needs
MW
m³/day
MMBTU/annum
Tons/Year